EstatePass
Contract AdminPreconstructionmedium27% of exam part

Alternate A adds $28,500 of scope and deletes $6,200 of base scope. With 10% overhead and profit on the net add, what additive alternate should be listed?

Correct Answer

C) $24,530 add

Compute net direct add, then add markup.

Answer Options
A
$22,300 add
B
$25,350 add
C
$24,530 add
D
$28,500 add

Why This Is the Correct Answer

Compute net direct add, then add markup.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.