Interior wall paint covers 365 sf per gallon. The net painted wall area is 14,235 sf and one coat is required. How many gallons should be estimated before tint overage?
Correct Answer
D) 39 gallons
One-coat quantity = 14,235 sf ÷ 365 sf/gallon = exactly 39 gallons. No fractional gallon remains to round up. Additional coats, tint overage or field losses are outside the stated estimate.
Why This Is the Correct Answer
One-coat quantity = 14,235 sf ÷ 365 sf/gallon = exactly 39 gallons. No fractional gallon remains to round up. Additional coats, tint overage or field losses are outside the stated estimate.
Independent practice; verify any reference hint against the edition and category permitted for your booking. Official exam and reference-list sources →
More Contract Admin Questions
A notice of nonpayment negligently omits a detail, and neither the contractor nor the surety is prejudiced. What is the effect on the claim?
A court enforces a lien against the improvement alone rather than the land. What may it order?
A general contractor wants an uncertified subcontractor to perform carpentry within the general contractor’s own licence scope. Does s. 489.113(2) allow it?
Who can compel a local government to create a residential master building permit program?
Which item is expressly listed as an example in the single-trade inspection definition in Florida Statutes section 553.791(1)(r)?
A contractor has Florida construction contracts with a city, a state department other than DOT, and a private owner. The private written contract is covered by section 715.12. Which listed provisions govern their respective prompt-payment regimes?
What must accompany a bid for construction on a Florida public project under s. 489.131(2)?
A Florida state agency buys ordinary nonconstruction goods under section 215.422. An undisputed, authorized invoice and the goods were received, inspected and approved on the same date. No vendor error or filing waiver applies. No warrant issues within 40 days. Which interest rule applies?
For a private-contract forecasting exercise, this period’s earned work is $258,400 and the stated holdback is 7.5%. With no prior-payment offsets or other deductions, what amount remains after retainage?
Under a Florida private written construction contract covered by section 715.12, an owner disputes drywall billing. Roofing payment is otherwise due and unaffected by that dispute; the contract has no contrary withholding term. May this dispute justify withholding the roofing payment?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Related Study Resources
Previous Question
Under section 713.16(1), an owner makes a qualifying written demand to its contractor for a subcontract copy and an ascertainable amount-due statement, and pays the reproduction cost. The contractor refuses, causing damages. Which remedy does that subsection provide?
Next Question
Interest is accruing under section 715.12 on an overdue Florida private construction payment. The applicable section 55.03 rate plus 12 percentage points is stipulated to be 17% annually; the contract specifies 18% annually. Which rate applies?