A private subcontract sets interest on late payment at 18 percent per annum, which is higher than the statutory rate that year. What does the obligee collect?

Correct Answer

C) The contract rate, since that is the greater of the two

Section 715.12(6)(a) provides that during the period interest accrues the rate is the s. 55.03 rate plus 12 percent per annum, or the rate specified in the contract, whichever is greater, and that a person is not entitled to receive both the contract interest and the statutory interest.

Answer Options
A
Both rates, the statute being cumulative with the contract
B
The statutory rate, which the contract cannot displace
C
The contract rate, since that is the greater of the two
D
The average of the contract rate and the statutory rate

Why This Is the Correct Answer

Section 715.12(6)(a) provides that during the period interest accrues the rate is the s. 55.03 rate plus 12 percent per annum, or the rate specified in the contract, whichever is greater, and that a person is not entitled to receive both the contract interest and the statutory interest.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.