Contract AdminPreconstructionmedium27% of exam part

A progress billing includes $258,400 of earned work. Retainage is 7.5%. What net amount should be forecast before other deductions?

Correct Answer

B) $239,020

Subtract retained amount from earned work.

Answer Options
A
$19,380
B
$239,020
C
$246,772
D
$258,400

Why This Is the Correct Answer

Subtract retained amount from earned work.

Why the Other Options Are Wrong

Option A: $19,380

$19,380 is below the supported result for cash-flow retainage; it likely uses the wrong base, period, or account bucket.

Option C: $246,772

$246,772 is above the supported result for cash-flow retainage; it likely adds an unsupported amount or compares the wrong financial base.

Option D: $258,400

$258,400 is above the supported result for cash-flow retainage; it likely adds an unsupported amount or compares the wrong financial base.

Memory Technique

Forecasts Cash money test: bucket before math for cash-flow retainage.

Reference Hint

Open-book path: tab Principles and Practices of Commercial Construction, 11th Edition, 2024 to Payment forecasting; retainage; verify the quantity, approval point, notice rule, or field record before answering.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.