A notice of nonpayment negligently omits a detail, and neither the contractor nor the surety is prejudiced. What is the effect on the claim?
Correct Answer
B) None, the omission is not a default defeating the claim
Section 713.23(1)(d) states that the negligent inclusion or omission of any information in the notice of nonpayment which has not prejudiced the contractor or surety does not constitute a default that operates to defeat an otherwise valid bond claim. Willful exaggeration is treated very differently.
Why This Is the Correct Answer
Section 713.23(1)(d) states that the negligent inclusion or omission of any information in the notice of nonpayment which has not prejudiced the contractor or surety does not constitute a default that operates to defeat an otherwise valid bond claim. Willful exaggeration is treated very differently.
Why the Other Options Are Wrong
Option A: The claim fails, the notice being a condition precedent
A non-prejudicial negligent omission does not defeat the claim.
Option C: The claim survives only for amounts stated correctly
The claim is not reduced for a non-prejudicial omission.
Option D: The claim is suspended until an amended notice is served
The statute does not suspend the claim for an amendment.
Independent practice; verify any reference hint against the edition and category permitted for your booking. Official exam and reference-list sources →
More Contract Admin Questions
A court enforces a lien against the improvement alone rather than the land. What may it order?
A general contractor wants an uncertified subcontractor to perform carpentry within the general contractor’s own licence scope. Does s. 489.113(2) allow it?
Who can compel a local government to create a residential master building permit program?
Which item is expressly listed as an example in the single-trade inspection definition in Florida Statutes section 553.791(1)(r)?
A contractor has Florida construction contracts with a city, a state department other than DOT, and a private owner. The private written contract is covered by section 715.12. Which listed provisions govern their respective prompt-payment regimes?
What must accompany a bid for construction on a Florida public project under s. 489.131(2)?
A Florida state agency buys ordinary nonconstruction goods under section 215.422. An undisputed, authorized invoice and the goods were received, inspected and approved on the same date. No vendor error or filing waiver applies. No warrant issues within 40 days. Which interest rule applies?
For a private-contract forecasting exercise, this period’s earned work is $258,400 and the stated holdback is 7.5%. With no prior-payment offsets or other deductions, what amount remains after retainage?
Under a Florida private written construction contract covered by section 715.12, an owner disputes drywall billing. Roofing payment is otherwise due and unaffected by that dispute; the contract has no contrary withholding term. May this dispute justify withholding the roofing payment?
A grade beam is 300 lf long, 24 in wide, and 18 in deep. Including 5% waste, how many cubic yards of concrete should be carried?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
