A notice of nonpayment negligently omits a detail, and neither the contractor nor the surety is prejudiced. What is the effect on the claim?
Correct Answer
B) None, the omission is not a default defeating the claim
Section 713.23(1)(d) states that the negligent inclusion or omission of any information in the notice of nonpayment which has not prejudiced the contractor or surety does not constitute a default that operates to defeat an otherwise valid bond claim. Willful exaggeration is treated very differently.
Why This Is the Correct Answer
Section 713.23(1)(d) states that the negligent inclusion or omission of any information in the notice of nonpayment which has not prejudiced the contractor or surety does not constitute a default that operates to defeat an otherwise valid bond claim. Willful exaggeration is treated very differently.
More Contract Admin Questions
When must a signal person be provided during a crane lift under subpart CC?
How may a signal person’s qualification be established under subpart CC?
What does subpart CC require to be carried on crane equipment itself?
A competent person’s excavation inspection finds evidence of a possible cave-in. What does s. 1926.651(k)(2) require?
What does a "permit application" comprise where a private provider has done the plan review?
A tenant asks the general contractor to begin demolition inside an existing space before the permit is issued. What does s. 553.79(1)(a) provide?
The enforcing agency determines that permitted work is not in conformity with the Florida Building Code. What may it do under s. 553.79(1)(a)?
A permit is denied because the plans are found not to comply. What must the local enforcing agency give the applicant?
What must a request for a certificate of occupancy include on a private provider job?
A rejected payment application is corrected and resubmitted to a city whose charter requires the commission to approve payments. When must the city pay or reject it?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass