A court enforces a lien against the improvement alone rather than the land. What may it order?

Correct Answer

D) Separate sale of the improvement, with removal in a fixed time

Section 713.11 allows the court enforcing such a lien to order the improvement to be separately sold, permits the purchaser to remove it within such reasonable time as the court fixes, and requires the purchase price to be paid into court.

Answer Options
A
A money judgment against the landowner for the improvement's value
B
Sale of the land together with the improvement to satisfy the lien
C
Forfeiture of the improvement to the landowner without payment
D
Separate sale of the improvement, with removal in a fixed time

Why This Is the Correct Answer

Section 713.11 allows the court enforcing such a lien to order the improvement to be separately sold, permits the purchaser to remove it within such reasonable time as the court fixes, and requires the purchase price to be paid into court.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.