A submittal is returned 'revise and resubmit' with comments affecting product selection. What should the GC do?

Correct Answer

B) Get a corrected resubmittal before procurement or installation

A revise-and-resubmit status means the item is not ready for unrestricted procurement or installation.

Answer Options
A
Order the original product because the first submittal was close enough for field use
B
Get a corrected resubmittal before procurement or installation
C
Treat the returned stamp as final acceptance and close the submittal log
D
Send the comments only to the accounting department for payment coding

Why This Is the Correct Answer

A revise-and-resubmit status means the item is not ready for unrestricted procurement or installation.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.