The permit documents call for inspection reports from an approved inspection agency. What is the GC's administrative duty?
Correct Answer
B) Coordinate required reports with the approved agency and keep them available for the code process
Special or required inspection reports must be coordinated as part of the permit and code-compliance process.
Why This Is the Correct Answer
Special or required inspection reports must be coordinated as part of the permit and code-compliance process.
Why the Other Options Are Wrong
Option A: Replace the reports with the daily cleanup log
Replace the reports with the daily cleanup log skips the written authority, scope, price, notice, or release control needed for threshold or special inspection coordination.
Option C: Submit the reports only after the owner occupies the building and final payment has been requested
Submit the reports only after the owner occupies the building and final payment has been requested skips the written authority, scope, price, notice, or release control needed for threshold or special inspection coordination.
Option D: Treat the concrete supplier ticket as the approved agency report
Treat the concrete supplier ticket as the approved agency report skips the written authority, scope, price, notice, or release control needed for threshold or special inspection coordination.
Memory Technique
Threshold Or Special square for Structural Includes: scope, authority, price, paper.
Reference Hint
Open-book path: tab Florida Building Code, Building, 8th Edition (2023) to Chapter 17 Special Inspections and Tests; Chapter 1 administration; match the role, timing, and required approval before choosing.
More Contract Admin Questions
An owner assumes the architect's site visit means the architect is supervising the contractor's crews. What AIA A201 concept corrects that assumption?
The GC and owner disagree about what a specification requires. Under AIA A201, who commonly provides interpretations and decisions during administration?
The architect observes work that does not conform to the Contract Documents. Which AIA A201 architect authority may apply?
A subcontractor says the prime contract general conditions do not apply to its work. Under AIA A401, what should the GC point to?
An addendum adds 18 access panels at $315 each installed. What amount should be added to the bid?
A slab-on-grade is 96 ft by 54 ft and 5 in thick. Including 7% waste, how many cubic yards of concrete should be carried?
An addendum adds 14 doors at $685 each installed. What additive amount should be added to the bid for those doors?
A CMU wall area is 2,240 sf after openings. If one block covers 1.125 sf and 4% waste is included, how many blocks should be estimated?
An office ceiling takeoff is 11,250 sf. Ceiling tile waste is 6%. How many square feet of tile should be carried?
A framing crew averages 310 lf of partition layout and track per day. The bid includes 2,170 lf. At $1,540 per crew day, what labor amount should be carried?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass