Who must sign the notice of commencement under Florida lien-law requirements?
Correct Answer
A) The owner must sign the notice of commencement
Chapter 713 states that the owner signs the notice of commencement.
Why This Is the Correct Answer
Chapter 713 states that the owner signs the notice of commencement.
Why the Other Options Are Wrong
Option B: The lowest bidder must sign because it controls bid security
The lowest bidder must sign because it controls bid security skips the written authority, scope, price, notice, or release control needed for notice signature.
Option C: The mechanical subcontractor must sign because it usually pulls trade permits
The mechanical subcontractor must sign because it usually pulls trade permits skips the written authority, scope, price, notice, or release control needed for notice signature.
Option D: The building inspector must sign before any permit application is processed
The building inspector must sign before any permit application is processed skips the written authority, scope, price, notice, or release control needed for notice signature.
Memory Technique
When states clashes with signs, let the contract speak before Permit Coordinator.
Reference Hint
Open-book path: tab Florida Statutes Chapter 713 to Β§713.13 Notice of commencement; match the role, timing, and required approval before choosing.
More Contract Admin Questions
An owner assumes the architect's site visit means the architect is supervising the contractor's crews. What AIA A201 concept corrects that assumption?
The GC and owner disagree about what a specification requires. Under AIA A201, who commonly provides interpretations and decisions during administration?
The architect observes work that does not conform to the Contract Documents. Which AIA A201 architect authority may apply?
A subcontractor says the prime contract general conditions do not apply to its work. Under AIA A401, what should the GC point to?
An addendum adds 18 access panels at $315 each installed. What amount should be added to the bid?
A slab-on-grade is 96 ft by 54 ft and 5 in thick. Including 7% waste, how many cubic yards of concrete should be carried?
An addendum adds 14 doors at $685 each installed. What additive amount should be added to the bid for those doors?
A CMU wall area is 2,240 sf after openings. If one block covers 1.125 sf and 4% waste is included, how many blocks should be estimated?
An office ceiling takeoff is 11,250 sf. Ceiling tile waste is 6%. How many square feet of tile should be carried?
A framing crew averages 310 lf of partition layout and track per day. The bid includes 2,170 lf. At $1,540 per crew day, what labor amount should be carried?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
