The parties disagree about a drawing requirement and ask for interpretation. Under AIA A201, which role commonly interprets and decides matters concerning performance?

Correct Answer

D) The Architect provides interpretations and decisions consistent with the Contract Documents

A201 assigns the Architect duties for interpretations and decisions during contract administration.

Answer Options
A
The lowest bidder interprets the document because it priced the project first
B
The county inspector decides all contract-payment disputes for the owner
C
Let the subcontractor's supplier issue final interpretations of disputed drawing requirements
D
The Architect provides interpretations and decisions consistent with the Contract Documents

Why This Is the Correct Answer

A201 assigns the Architect duties for interpretations and decisions during contract administration.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.