The permit drawings and a later field sketch disagree on a rated wall detail. What should the GC do before building the changed detail?

Correct Answer

C) Coordinate an approved revision or clarification through the design and permit process

Regulated construction should follow approved construction documents or properly approved revisions.

Answer Options
A
Build the sketch first because any newer paper automatically overrides approved permit documents
B
Ask the supplier to certify the rated assembly from memory after installation
C
Coordinate an approved revision or clarification through the design and permit process
D
Hide the conflict until the final inspection so the inspector can choose a version

Why This Is the Correct Answer

Regulated construction should follow approved construction documents or properly approved revisions.

Why the Other Options Are Wrong

Option A: Build the sketch first because any newer paper automatically overrides approved permit documents

Build the sketch first because any newer paper automatically overrides approved permit documents skips the written authority, scope, price, notice, or release control needed for construction document conflict.

Option B: Ask the supplier to certify the rated assembly from memory after installation

Ask the supplier to certify the rated assembly from memory after installation skips the written authority, scope, price, notice, or release control needed for construction document conflict.

Option D: Hide the conflict until the final inspection so the inspector can choose a version

Hide the conflict until the final inspection so the inspector can choose a version skips the written authority, scope, price, notice, or release control needed for construction document conflict.

Memory Technique

Superintendent Finds shortcut is not a term until paper carries it.

Reference Hint

Open-book path: tab Florida Building Code, Building, 8th Edition (2023), Chapter 1 Administration to Chapter 1 Section 107 construction documents; confirm the required quantity, authority, timing, or record before selecting the answer.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.