A plumbing subpermit is not final, but the GC wants the overall final inspection. What should the PM verify?

Correct Answer

C) Required trade permit finals and inspection approvals are complete before requesting overall closeout approval

Overall closeout depends on required permit and trade inspection approvals.

Answer Options
A
The plumbing supplier has sent its final invoice before any inspection status is checked or approved
B
The estimator has deleted the plumbing line from the schedule of values
C
Required trade permit finals and inspection approvals are complete before requesting overall closeout approval
D
The original bid tabulation lists a plumbing bidder even if no inspection is final

Why This Is the Correct Answer

Overall closeout depends on required permit and trade inspection approvals.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.