Soon after award, the owner requests the GC's plan for sequencing the Work. Which AIA A201 contractor duty is triggered?

Correct Answer

A) Prepare and submit the contractor's construction schedule for the Work

A201 requires the Contractor to prepare and submit a construction schedule.

Answer Options
A
Prepare and submit the contractor's construction schedule for the Work
B
Issue a substantial-completion certificate before mobilization instead of a construction schedule
C
Replace the baseline schedule with a subcontract invoice log
D
Withdraw the bid because schedule preparation occurs before award only

Why This Is the Correct Answer

A201 requires the Contractor to prepare and submit a construction schedule.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.