A required inspection is needed before concrete placement. What should the superintendent do?
Correct Answer
C) Request and obtain the required inspection approval before placing concrete
Required inspections should occur before work proceeds past the inspection point.
Why This Is the Correct Answer
Required inspections should occur before work proceeds past the inspection point.
Why the Other Options Are Wrong
Option A: Place concrete first and ask the inspector to review photographs later
Place concrete first and ask the inspector to review photographs later addresses a neighboring field issue, but not the condition or method control required for inspection request timing.
Option B: Use the concrete delivery ticket as inspection approval
Use the concrete delivery ticket as inspection approval addresses a neighboring field issue, but not the condition or method control required for inspection request timing.
Option D: Wait until the final certificate of occupancy inspection to mention the missed inspection
Wait until the final certificate of occupancy inspection to mention the missed inspection addresses a neighboring field issue, but not the condition or method control required for inspection request timing.
Memory Technique
The field condition asks; inspection request answers in work boots for Foundation Pour.
Reference Hint
Open-book path: tab Florida Building Code, Building, 8th Edition (2023), Chapter 1 Administration to Chapter 1, Β§110 Inspections; match the role, timing, and required approval before choosing.
More Contract Admin Questions
An owner assumes the architect's site visit means the architect is supervising the contractor's crews. What AIA A201 concept corrects that assumption?
The GC and owner disagree about what a specification requires. Under AIA A201, who commonly provides interpretations and decisions during administration?
The architect observes work that does not conform to the Contract Documents. Which AIA A201 architect authority may apply?
A subcontractor says the prime contract general conditions do not apply to its work. Under AIA A401, what should the GC point to?
An addendum adds 18 access panels at $315 each installed. What amount should be added to the bid?
A slab-on-grade is 96 ft by 54 ft and 5 in thick. Including 7% waste, how many cubic yards of concrete should be carried?
An addendum adds 14 doors at $685 each installed. What additive amount should be added to the bid for those doors?
A CMU wall area is 2,240 sf after openings. If one block covers 1.125 sf and 4% waste is included, how many blocks should be estimated?
An office ceiling takeoff is 11,250 sf. Ceiling tile waste is 6%. How many square feet of tile should be carried?
A framing crew averages 310 lf of partition layout and track per day. The bid includes 2,170 lf. At $1,540 per crew day, what labor amount should be carried?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A layout crew completes 255 lf of wall layout per day. The project has 1,785 lf. At $1,680 per crew day, what labor amount should be carried?
Next Question
A Florida notice of commencement is recorded for a project. When is the giving of the notice generally effective under Chapter 713?