A layout crew completes 255 lf of wall layout per day. The project has 1,785 lf. At $1,680 per crew day, what labor amount should be carried?

Correct Answer

C) $11,760

Divide quantity by daily production and multiply by crew-day cost.

Answer Options
A
$10,080
B
$12,600
C
$11,760
D
$13,440

Why This Is the Correct Answer

Divide quantity by daily production and multiply by crew-day cost.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.