A required above-ceiling inspection is scheduled, but ceiling tile installation would conceal the work. What should the superintendent do?

Correct Answer

D) Keep the work accessible until required inspection and approval are complete

FBC inspection provisions require work to remain available for required inspection.

Answer Options
A
Install the ceiling tile and offer photos if the inspector asks later
B
Delete the inspection from the look-ahead schedule because finish work is more visible
C
Use the subcontractor invoice as proof that concealed work passed
D
Keep the work accessible until required inspection and approval are complete

Why This Is the Correct Answer

FBC inspection provisions require work to remain available for required inspection.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.