EstatePass
Contract AdminPreconstructionmedium27% of exam part

The plans require 1,575 cy of compacted structural fill. Borrow material yields 87% after placement and compaction. How many loose cubic yards should be purchased?

Correct Answer

A) 1,810 lcy

Divide compacted required volume by the compaction yield.

Answer Options
A
1,810 lcy
B
1,370 lcy
C
1,575 lcy
D
1,902 lcy

Why This Is the Correct Answer

Divide compacted required volume by the compaction yield.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.