Roofing material will arrive before the deck is ready and storage space is limited. What should the PM do?
Correct Answer
D) Coordinate delivery timing, storage location, protection, and handling before release
Material delivery should be sequenced with site readiness and protection.
Why This Is the Correct Answer
Material delivery should be sequenced with site readiness and protection.
Why the Other Options Are Wrong
Option A: Accept the delivery anywhere onsite and solve damage issues at final payment
Accept the delivery anywhere onsite and solve damage issues at final payment addresses a neighboring field issue, but not the condition or method control required for delivery sequencing.
Option B: Let the carrier choose the storage area without site coordination
Let the carrier choose the storage area without site coordination addresses a neighboring field issue, but not the condition or method control required for delivery sequencing.
Option C: Release all material early because procurement records matter more than protection, sequence, or storage
Release all material early because procurement records matter more than protection, sequence, or storage addresses a neighboring field issue, but not the condition or method control required for delivery sequencing.
Memory Technique
The field condition asks; delivery sequencing answers in work boots for Manages Roofing.
Reference Hint
Open-book path: tab Principles and Practices of Commercial Construction, 11th Edition, 2024 to Construction operations; procurement, delivery, storage, and handling; match the role, timing, and required approval before choosing.
More Contract Admin Questions
An owner assumes the architect's site visit means the architect is supervising the contractor's crews. What AIA A201 concept corrects that assumption?
The GC and owner disagree about what a specification requires. Under AIA A201, who commonly provides interpretations and decisions during administration?
The architect observes work that does not conform to the Contract Documents. Which AIA A201 architect authority may apply?
A subcontractor says the prime contract general conditions do not apply to its work. Under AIA A401, what should the GC point to?
An addendum adds 18 access panels at $315 each installed. What amount should be added to the bid?
A slab-on-grade is 96 ft by 54 ft and 5 in thick. Including 7% waste, how many cubic yards of concrete should be carried?
An addendum adds 14 doors at $685 each installed. What additive amount should be added to the bid for those doors?
A CMU wall area is 2,240 sf after openings. If one block covers 1.125 sf and 4% waste is included, how many blocks should be estimated?
An office ceiling takeoff is 11,250 sf. Ceiling tile waste is 6%. How many square feet of tile should be carried?
A framing crew averages 310 lf of partition layout and track per day. The bid includes 2,170 lf. At $1,540 per crew day, what labor amount should be carried?