The owner complains that construction waste is accumulating in occupied adjacent space. Which AIA A201 contractor duty applies?
Correct Answer
B) Keep the premises and surrounding area free from waste materials and rubbish caused by operations
A201 includes a Contractor duty to keep the site and surrounding area free of waste and rubbish caused by operations.
Why This Is the Correct Answer
A201 includes a Contractor duty to keep the site and surrounding area free of waste and rubbish caused by operations.
Why the Other Options Are Wrong
Option A: Let construction waste remain until final completion even when it affects occupied areas
Let construction waste remain until final completion even when it affects occupied areas skips the written authority, scope, price, notice, or release control needed for cleaning up.
Option C: Make the architect responsible for jobsite housekeeping after each observation
Make the architect responsible for jobsite housekeeping after each observation skips the written authority, scope, price, notice, or release control needed for cleaning up.
Option D: Charge cleanup only to the owner's lender and exclude it from contract duties
Charge cleanup only to the owner's lender and exclude it from contract duties skips the written authority, scope, price, notice, or release control needed for cleaning up.
Memory Technique
Cleaning Up square for Interior Renovation: scope, authority, price, paper.
Reference Hint
Open-book path: tab AIA A201-2017 to Article 3, Β§3.15 Cleaning Up; match the contract role and timing in the stem before choosing.
More Contract Admin Questions
An owner assumes the architect's site visit means the architect is supervising the contractor's crews. What AIA A201 concept corrects that assumption?
The GC and owner disagree about what a specification requires. Under AIA A201, who commonly provides interpretations and decisions during administration?
The architect observes work that does not conform to the Contract Documents. Which AIA A201 architect authority may apply?
A subcontractor says the prime contract general conditions do not apply to its work. Under AIA A401, what should the GC point to?
An addendum adds 18 access panels at $315 each installed. What amount should be added to the bid?
A slab-on-grade is 96 ft by 54 ft and 5 in thick. Including 7% waste, how many cubic yards of concrete should be carried?
An addendum adds 14 doors at $685 each installed. What additive amount should be added to the bid for those doors?
A CMU wall area is 2,240 sf after openings. If one block covers 1.125 sf and 4% waste is included, how many blocks should be estimated?
An office ceiling takeoff is 11,250 sf. Ceiling tile waste is 6%. How many square feet of tile should be carried?
A framing crew averages 310 lf of partition layout and track per day. The bid includes 2,170 lf. At $1,540 per crew day, what labor amount should be carried?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass