A steel quote is $142,000 and the estimator carries a 4% escalation allowance before award. What amount should be carried for steel?

Correct Answer

D) $147,680

Add the escalation allowance to the quoted price.

Answer Options
A
$136,320
B
$145,550
C
$153,360
D
$147,680

Why This Is the Correct Answer

Add the escalation allowance to the quoted price.

Why the Other Options Are Wrong

Option A: $136,320

$136,320 is below the supported result for material escalation; it likely omits part of the approved scope, cap, credit, or holdback.

Option B: $145,550

$145,550 is below the supported result for material escalation; it likely omits part of the approved scope, cap, credit, or holdback.

Option C: $153,360

$153,360 is above the supported result for material escalation; it likely adds scope or money the rule does not allow.

Memory Technique

Prices Delayed-Award contract math: approved scope is the ruler for material escalation.

Reference Hint

Open-book path: tab Principles and Practices of Commercial Construction, 11th Edition, 2024 to Preconstruction estimating; escalation allowance; match the role, timing, and required approval before choosing.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.