EstatePass
Contract AdminContractsmedium40% of exam part

A Florida GC wants to reuse the architect's project drawings on an unrelated private job. Which AIA A201 topic limits that idea?

Correct Answer

C) Ownership and permitted use of drawings, specifications, and other instruments of service

A201 addresses ownership and permitted use of the design professional's documents.

Answer Options
A
The schedule of values used only for monthly applications for payment, and use that shortcut to decide the drawings requirement, without documenting the decision in the change or claim record
B
The bidder's right to withdraw a proposal before the bid deadline
C
Ownership and permitted use of drawings, specifications, and other instruments of service
D
The subcontractor's warranty of its own material deliveries, and make the pricing assumption binding without approval

Why This Is the Correct Answer

A201 addresses ownership and permitted use of the design professional's documents.

Why the Other Options Are Wrong

Option A: The schedule of values used only for monthly applications for payment, and use that shortcut to decide the drawings requirement, without documenting the decision in the change or claim record

The schedule of values used only for monthly applications for payment, and use that shortcut to decide the drawings requirement, without documenting the decision in the change or claim record skips the written authority, scope, price, notice, or release control needed for ownership and use of documents.

Option B: The bidder's right to withdraw a proposal before the bid deadline

The bidder's right to withdraw a proposal before the bid deadline skips the written authority, scope, price, notice, or release control needed for ownership and use of documents.

Option D: The subcontractor's warranty of its own material deliveries, and make the pricing assumption binding without approval

The subcontractor's warranty of its own material deliveries, and make the pricing assumption binding without approval skips the written authority, scope, price, notice, or release control needed for ownership and use of documents.

Memory Technique

Asks Whether shortcut is not a term until paper carries it.

Reference Hint

Open-book path: tab AIA A201-2017 to Article 1, Β§1.5 Ownership and Use of Drawings, Specifications, and Other Instruments of Service; match the contract role, notice step, and timing in the stem before choosing.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.