Alternate No. 2 removes a scope item with $38,000 direct cost. The bid form requires overhead and profit at 10% on alternates. What deductive alternate amount should be listed?

Correct Answer

C) $41,800 deduct

The alternate deduct includes direct cost plus the required overhead and profit.

Answer Options
A
$34,200 deduct
B
$38,000 deduct
C
$41,800 deduct
D
$45,600 deduct

Why This Is the Correct Answer

The alternate deduct includes direct cost plus the required overhead and profit.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.