Contract AdminPreconstructionmedium27% of exam part

A permit allowance is 0.85% of a $3,250,000 construction value. What allowance should be included?

Correct Answer

D) $27,625

Multiply construction value by rate.

Answer Options
A
$24,375
B
$29,250
C
$32,500
D
$27,625

Why This Is the Correct Answer

Multiply construction value by rate.

Why the Other Options Are Wrong

Option A: $24,375

$24,375 is below the supported result for permit allowance; it likely omits part of the approved scope, cap, credit, or holdback.

Option B: $29,250

$29,250 is above the supported result for permit allowance; it likely adds scope or money the rule does not allow.

Option C: $32,500

$32,500 is above the supported result for permit allowance; it likely adds scope or money the rule does not allow.

Memory Technique

Permit Allowance gate for Gmp Worksheet: paper opens before money moves.

Reference Hint

Open-book path: tab Principles and Practices of Commercial Construction, 11th Edition, 2024 to General conditions estimating; permit allowance; verify quantity math, FL permit status, notice step, or field-control timing.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.