EstatePass
Contract AdminContractsmedium40% of exam part

A long-lead storefront package must be reviewed early. Under AIA A201, what schedule helps coordinate that review?

Correct Answer

B) The submittal schedule showing when shop drawings and product data will be submitted

A201 uses a submittal schedule to coordinate shop drawing, product data, and sample submissions.

Answer Options
A
The final punch-list schedule issued after substantial completion
B
The submittal schedule showing when shop drawings and product data will be submitted
C
The bidder list used only before the owner awards the contract
D
Use the final lien-release log as the tool for coordinating early storefront submittals

Why This Is the Correct Answer

A201 uses a submittal schedule to coordinate shop drawing, product data, and sample submissions.

Why the Other Options Are Wrong

Option A: The final punch-list schedule issued after substantial completion

The final punch-list schedule issued after substantial completion skips the written authority, scope, price, notice, or release control needed for submittal schedule.

Option C: The bidder list used only before the owner awards the contract

The bidder list used only before the owner awards the contract skips the written authority, scope, price, notice, or release control needed for submittal schedule.

Option D: Use the final lien-release log as the tool for coordinating early storefront submittals

Use the final lien-release log as the tool for coordinating early storefront submittals skips the written authority, scope, price, notice, or release control needed for submittal schedule.

Memory Technique

Coordinating Long-Lead shortcut is not a term until paper carries it.

Reference Hint

Open-book path: tab AIA A201-2017 to Article 3, §3.10 and §3.12 Contractor's Submittal Schedule and Submittals; match the contract role and timing in the stem before choosing.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.