Contract AdminProceduresmedium13% of exam part

Several owner-directed changes are authorized at different stages. What record helps the PM manage pricing and approval status?

Correct Answer

B) Use a change log for scope, pricing, approval, and schedule impact

A change log tracks pending and approved changes through pricing and authorization.

Answer Options
A
A single final invoice with no reference to authorization or scope history
B
Use a change log for scope, pricing, approval, and schedule impact
C
A subcontractor contact list because it replaces the change-management record
D
A weather log because all owner changes are treated as rain delays

Why This Is the Correct Answer

A change log tracks pending and approved changes through pricing and authorization.

Why the Other Options Are Wrong

Option A: A single final invoice with no reference to authorization or scope history

A single final invoice with no reference to authorization or scope history skips the written authority, scope, price, notice, or release control needed for change-order log.

Option C: A subcontractor contact list because it replaces the change-management record

A subcontractor contact list because it replaces the change-management record skips the written authority, scope, price, notice, or release control needed for change-order log.

Option D: A weather log because all owner changes are treated as rain delays

A weather log because all owner changes are treated as rain delays skips the written authority, scope, price, notice, or release control needed for change-order log.

Memory Technique

Manages Multiple shortcut is not a term until paper carries it.

Reference Hint

Open-book path: tab Principles and Practices of Commercial Construction, 11th Edition, 2024 to Field administration; change-order log and authorization tracking; confirm the required quantity, authority, timing, or record before selecting the answer.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.