A local jurisdiction identifies administrative requirements in addition to the base Florida Building Code. What should the GC do?
Correct Answer
D) Check applicable local administrative provisions and approved permit requirements before proceeding
Florida code administration can include local administrative requirements that affect permit workflow.
Why This Is the Correct Answer
Florida code administration can include local administrative requirements that affect permit workflow.
Why the Other Options Are Wrong
Option A: Ignore local administrative requirements because only the subcontract proposal matters during permit review
Ignore local administrative requirements because only the subcontract proposal matters during permit review skips the written authority, scope, price, notice, or release control needed for local amendments.
Option B: Use the bid bond form to override local permit procedures
Use the bid bond form to override local permit procedures skips the written authority, scope, price, notice, or release control needed for local amendments.
Option C: Wait until after occupancy to ask whether local forms were required
Wait until after occupancy to ask whether local forms were required skips the written authority, scope, price, notice, or release control needed for local amendments.
Memory Technique
Jurisdiction Specific shortcut is not a term until paper carries it.
Reference Hint
Open-book path: tab Florida Building Code, Building, 8th Edition (2023), Chapter 1 Administration to Chapter 1 Scope and Administration; local administrative requirements; match the role, timing, and required approval before choosing.
More Contract Admin Questions
An owner assumes the architect's site visit means the architect is supervising the contractor's crews. What AIA A201 concept corrects that assumption?
The GC and owner disagree about what a specification requires. Under AIA A201, who commonly provides interpretations and decisions during administration?
The architect observes work that does not conform to the Contract Documents. Which AIA A201 architect authority may apply?
A subcontractor says the prime contract general conditions do not apply to its work. Under AIA A401, what should the GC point to?
An addendum adds 18 access panels at $315 each installed. What amount should be added to the bid?
A slab-on-grade is 96 ft by 54 ft and 5 in thick. Including 7% waste, how many cubic yards of concrete should be carried?
An addendum adds 14 doors at $685 each installed. What additive amount should be added to the bid for those doors?
A CMU wall area is 2,240 sf after openings. If one block covers 1.125 sf and 4% waste is included, how many blocks should be estimated?
An office ceiling takeoff is 11,250 sf. Ceiling tile waste is 6%. How many square feet of tile should be carried?
A framing crew averages 310 lf of partition layout and track per day. The bid includes 2,170 lf. At $1,540 per crew day, what labor amount should be carried?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass