EstatePass
Contract AdminContractsmedium40% of exam part

The owner and GC agree on a revised storefront detail, a $18,000 increase, and no time change. Which AIA A201 instrument should record the agreement?

Correct Answer

D) A Change Order signed or otherwise agreed as the contract requires

A Change Order records agreed changes in Work, Contract Sum, or Contract Time.

Answer Options
A
A field report that notes the condition without modifying the Contract Sum
B
A bid addendum issued to bidders after construction has started
C
A certificate of substantial completion for the changed storefront work
D
A Change Order signed or otherwise agreed as the contract requires

Why This Is the Correct Answer

A Change Order records agreed changes in Work, Contract Sum, or Contract Time.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.