The GC receives a payment certificate from the architect. Under AIA A201, which general role is the architect performing?
Correct Answer
C) Administering the Contract as described in the Contract Documents
A201 describes the Architect's role in administration of the Contract.
Why This Is the Correct Answer
A201 describes the Architect's role in administration of the Contract.
Why the Other Options Are Wrong
Option A: Replacing the Contractor's means-and-methods responsibility at the site
Replacing the Contractor's means-and-methods responsibility at the site skips the written authority, scope, price, notice, or release control needed for architect administration.
Option B: Becoming the surety for the contractor's payment obligations
Becoming the surety for the contractor's payment obligations skips the written authority, scope, price, notice, or release control needed for architect administration.
Option D: Issuing bidder instructions after the construction contract is complete
Issuing bidder instructions after the construction contract is complete skips the written authority, scope, price, notice, or release control needed for architect administration.
Memory Technique
Architect Administration square for Team Routes: scope, authority, price, paper.
Reference Hint
Open-book path: tab AIA A201-2017 to Article 4, Β§4.2 Administration of the Contract; match the contract role and timing in the stem before choosing.
More Contract Admin Questions
An owner assumes the architect's site visit means the architect is supervising the contractor's crews. What AIA A201 concept corrects that assumption?
The GC and owner disagree about what a specification requires. Under AIA A201, who commonly provides interpretations and decisions during administration?
The architect observes work that does not conform to the Contract Documents. Which AIA A201 architect authority may apply?
A subcontractor says the prime contract general conditions do not apply to its work. Under AIA A401, what should the GC point to?
An addendum adds 18 access panels at $315 each installed. What amount should be added to the bid?
A slab-on-grade is 96 ft by 54 ft and 5 in thick. Including 7% waste, how many cubic yards of concrete should be carried?
An addendum adds 14 doors at $685 each installed. What additive amount should be added to the bid for those doors?
A CMU wall area is 2,240 sf after openings. If one block covers 1.125 sf and 4% waste is included, how many blocks should be estimated?
An office ceiling takeoff is 11,250 sf. Ceiling tile waste is 6%. How many square feet of tile should be carried?
A framing crew averages 310 lf of partition layout and track per day. The bid includes 2,170 lf. At $1,540 per crew day, what labor amount should be carried?