A field dimension conflicts with a drawing note, and the answer affects fabrication. What should the PM do?

Correct Answer

A) Submit and track an RFI before fabrication proceeds

Formal clarification prevents fabrication from proceeding on an unresolved document conflict.

Answer Options
A
Submit and track an RFI before fabrication proceeds
B
Let the fabricator pick the cheapest interpretation and correct it after delivery
C
Use the daily cleanup checklist as the official design clarification
D
Wait until punch list to ask whether the dimension was important

Why This Is the Correct Answer

Formal clarification prevents fabrication from proceeding on an unresolved document conflict.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.