A subcontractor sends a shop drawing directly to the architect without GC coordination. What contract control is missing?

Correct Answer

D) Complete GC submittal review first

A201 requires contractor review and approval before submittals go to the Architect.

Answer Options
A
Owner financing approval of the shop drawing
B
Permit clerk approval of trade coordination
C
Bidder certification after contract award
D
Complete GC submittal review first

Why This Is the Correct Answer

A201 requires contractor review and approval before submittals go to the Architect.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.