The architect issues punch-list items assigned to three trades. What is the best control for the GC?

Correct Answer

D) Track each punch item through assignment, completion, and verification

Punch-list control requires assignment, completion, and verification.

Answer Options
A
Send the entire list to the owner and stop tracking because the architect created it
B
Close every item when the first trade says its work is finished
C
Move the list to warranty records without field verification
D
Track each punch item through assignment, completion, and verification

Why This Is the Correct Answer

Punch-list control requires assignment, completion, and verification.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.