EstatePass
Contract AdminProceduresmedium13% of exam part

The contract requires submittal clearance before fabrication. A product submittal returns revise-and-resubmit, with no partial release authorized. What should the GC do about this item?

Correct Answer

B) Hold the affected fabrication release until the required resubmittal review clears it.

Hold fabrication of the affected item, distribute the review comments and obtain the required resubmittal clearance. Update the log and schedule impact. Unaffected procurement need not be stopped, and a supplier invoice is not approval.

Answer Options
A
Release it using the rejected submittal.
B
Hold the affected fabrication release until the required resubmittal review clears it.
C
Treat the supplier invoice as approval.
D
Close the log without distributing comments.

Why This Is the Correct Answer

Hold fabrication of the affected item, distribute the review comments and obtain the required resubmittal clearance. Update the log and schedule impact. Unaffected procurement need not be stopped, and a supplier invoice is not approval.

Independent practice; verify any reference hint against the edition and category permitted for your booking. Official exam and reference-list sources →

Was this explanation helpful?

More Contract Admin Questions

A notice of nonpayment negligently omits a detail, and neither the contractor nor the surety is prejudiced. What is the effect on the claim?

A court enforces a lien against the improvement alone rather than the land. What may it order?

A general contractor wants an uncertified subcontractor to perform carpentry within the general contractor’s own licence scope. Does s. 489.113(2) allow it?

Who can compel a local government to create a residential master building permit program?

Which item is expressly listed as an example in the single-trade inspection definition in Florida Statutes section 553.791(1)(r)?

A contractor has Florida construction contracts with a city, a state department other than DOT, and a private owner. The private written contract is covered by section 715.12. Which listed provisions govern their respective prompt-payment regimes?

What must accompany a bid for construction on a Florida public project under s. 489.131(2)?

A Florida state agency buys ordinary nonconstruction goods under section 215.422. An undisputed, authorized invoice and the goods were received, inspected and approved on the same date. No vendor error or filing waiver applies. No warrant issues within 40 days. Which interest rule applies?

For a private-contract forecasting exercise, this period’s earned work is $258,400 and the stated holdback is 7.5%. With no prior-payment offsets or other deductions, what amount remains after retainage?

Under a Florida private written construction contract covered by section 715.12, an owner disputes drywall billing. Roofing payment is otherwise due and unaffected by that dispute; the contract has no contrary withholding term. May this dispute justify withholding the roofing payment?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.