A contract and permit application list different contracting business names for the same work. What is the licensing concern?
Correct Answer
A) The responsible licensed business organization and qualifier should be consistent and accurate
Florida contractor licensing and permit records should identify the responsible licensed entity accurately.
Why This Is the Correct Answer
Florida contractor licensing and permit records should identify the responsible licensed entity accurately.
Why the Other Options Are Wrong
Option B: Different names are always acceptable if the material supplier approves them and invoices the correct project
Different names are always acceptable if the material supplier approves them and invoices the correct project skips the written authority, scope, price, notice, or release control needed for license name on contract.
Option C: The discrepancy is solved by increasing the contingency line item
The discrepancy is solved by increasing the contingency line item skips the written authority, scope, price, notice, or release control needed for license name on contract.
Option D: The certificate of occupancy replaces contractor licensing records
The certificate of occupancy replaces contractor licensing records skips the written authority, scope, price, notice, or release control needed for license name on contract.
Memory Technique
License Name On square for Owner Asks: scope, authority, price, paper.
Reference Hint
Open-book path: tab Florida Statutes Chapter 489 to Part I, business organizations and qualifying agents; match the role, timing, and required approval before choosing.
More Contract Admin Questions
An owner assumes the architect's site visit means the architect is supervising the contractor's crews. What AIA A201 concept corrects that assumption?
The GC and owner disagree about what a specification requires. Under AIA A201, who commonly provides interpretations and decisions during administration?
The architect observes work that does not conform to the Contract Documents. Which AIA A201 architect authority may apply?
A subcontractor says the prime contract general conditions do not apply to its work. Under AIA A401, what should the GC point to?
An addendum adds 18 access panels at $315 each installed. What amount should be added to the bid?
A slab-on-grade is 96 ft by 54 ft and 5 in thick. Including 7% waste, how many cubic yards of concrete should be carried?
An addendum adds 14 doors at $685 each installed. What additive amount should be added to the bid for those doors?
A CMU wall area is 2,240 sf after openings. If one block covers 1.125 sf and 4% waste is included, how many blocks should be estimated?
An office ceiling takeoff is 11,250 sf. Ceiling tile waste is 6%. How many square feet of tile should be carried?
A framing crew averages 310 lf of partition layout and track per day. The bid includes 2,170 lf. At $1,540 per crew day, what labor amount should be carried?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass