A pipe route changes in the field with approved direction. What should the GC do with record documents?

Correct Answer

A) Update record drawings or as-built information while the change is current

Record documents should be updated as changes occur.

Answer Options
A
Update record drawings or as-built information while the change is current
B
Wait until final payment and reconstruct the route from memory
C
Use the original bid drawing even though it no longer matches the work
D
Ask the drywall subcontractor to certify all concealed piping locations without updating the record documents

Why This Is the Correct Answer

Record documents should be updated as changes occur.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.