A trade falls behind because it is not staffing the work as planned. What is the best operational response?
Correct Answer
D) Document the issue, coordinate recovery actions, and escalate under the subcontract procedure if needed
Construction operations require documented schedule recovery and subcontract coordination.
Why This Is the Correct Answer
Construction operations require documented schedule recovery and subcontract coordination.
Why the Other Options Are Wrong
Option A: Ignore the issue until the final completion date passes
Ignore the issue until the final completion date passes relies on the wrong note, symbol, sheet, scale, or detail path for subcontractor manpower issue.
Option B: Have another trade perform the work without notice, coordination, schedule recovery, or subcontract procedure
Have another trade perform the work without notice, coordination, schedule recovery, or subcontract procedure relies on the wrong note, symbol, sheet, scale, or detail path for subcontractor manpower issue.
Option C: Change the permit drawings to match the delayed manpower level
Change the permit drawings to match the delayed manpower level relies on the wrong note, symbol, sheet, scale, or detail path for subcontractor manpower issue.
Memory Technique
Subcontractor Manpower trail for Superintendent Sees: note to schedule to detail, then field action.
Reference Hint
Open-book path: tab Principles and Practices of Commercial Construction, 11th Edition, 2024 to Construction scheduling and subcontractor coordination; recovery planning; match the role, timing, and required approval before choosing.
More Contract Admin Questions
An owner assumes the architect's site visit means the architect is supervising the contractor's crews. What AIA A201 concept corrects that assumption?
The GC and owner disagree about what a specification requires. Under AIA A201, who commonly provides interpretations and decisions during administration?
The architect observes work that does not conform to the Contract Documents. Which AIA A201 architect authority may apply?
A subcontractor says the prime contract general conditions do not apply to its work. Under AIA A401, what should the GC point to?
An addendum adds 18 access panels at $315 each installed. What amount should be added to the bid?
A slab-on-grade is 96 ft by 54 ft and 5 in thick. Including 7% waste, how many cubic yards of concrete should be carried?
An addendum adds 14 doors at $685 each installed. What additive amount should be added to the bid for those doors?
A CMU wall area is 2,240 sf after openings. If one block covers 1.125 sf and 4% waste is included, how many blocks should be estimated?
An office ceiling takeoff is 11,250 sf. Ceiling tile waste is 6%. How many square feet of tile should be carried?
A framing crew averages 310 lf of partition layout and track per day. The bid includes 2,170 lf. At $1,540 per crew day, what labor amount should be carried?