A crane has 3 standby days at $1,950 per day after a delivery delay. If a change estimate includes those standby days only, what amount is requested?

Correct Answer

B) $5,850

Multiply standby days by the daily standby rate.

Answer Options
A
$3,900
B
$5,850
C
$4,875
D
$7,800

Why This Is the Correct Answer

Multiply standby days by the daily standby rate.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.