The owner verbally asks for added millwork during a walk-through. What should the PM do before release?

Correct Answer

B) Document and obtain required written authorization

Owner-directed changes should be documented and authorized through the contract process.

Answer Options
A
Proceed from memory and price it at final payment
B
Document and obtain required written authorization
C
Use the daily weather report as authorization
D
Ask the cabinet supplier to approve the owner change

Why This Is the Correct Answer

Owner-directed changes should be documented and authorized through the contract process.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.