The tenant wants to use the space after final inspection corrections are complete. Which approval should the GC confirm before occupancy when required?
Correct Answer
D) Certificate of occupancy or other required approval from the building official
FBC administration governs occupancy approval through certificates or required approvals.
Why This Is the Correct Answer
FBC administration governs occupancy approval through certificates or required approvals.
Why the Other Options Are Wrong
Option A: The last subcontractor invoice with all retainage billed
The last subcontractor invoice with all retainage billed skips the written authority, scope, price, notice, or release control needed for certificate of occupancy scope.
Option B: The estimator's final bid recap and unit-price backup
The estimator's final bid recap and unit-price backup skips the written authority, scope, price, notice, or release control needed for certificate of occupancy scope.
Option C: The supplier's warranty registration for installed materials, product data, and closeout manuals only
The supplier's warranty registration for installed materials, product data, and closeout manuals only skips the written authority, scope, price, notice, or release control needed for certificate of occupancy scope.
Memory Technique
the controlling record square for Retail Tenant: scope, authority, price, paper.
Reference Hint
Open-book path: tab Florida Building Code, Building, 8th Edition (2023), Chapter 1 Administration to Chapter 1, Β§111 Certificate of Occupancy; match the role, timing, and required approval before choosing.
More Contract Admin Questions
An owner assumes the architect's site visit means the architect is supervising the contractor's crews. What AIA A201 concept corrects that assumption?
The GC and owner disagree about what a specification requires. Under AIA A201, who commonly provides interpretations and decisions during administration?
The architect observes work that does not conform to the Contract Documents. Which AIA A201 architect authority may apply?
A subcontractor says the prime contract general conditions do not apply to its work. Under AIA A401, what should the GC point to?
An addendum adds 18 access panels at $315 each installed. What amount should be added to the bid?
A slab-on-grade is 96 ft by 54 ft and 5 in thick. Including 7% waste, how many cubic yards of concrete should be carried?
An addendum adds 14 doors at $685 each installed. What additive amount should be added to the bid for those doors?
A CMU wall area is 2,240 sf after openings. If one block covers 1.125 sf and 4% waste is included, how many blocks should be estimated?
An office ceiling takeoff is 11,250 sf. Ceiling tile waste is 6%. How many square feet of tile should be carried?
A framing crew averages 310 lf of partition layout and track per day. The bid includes 2,170 lf. At $1,540 per crew day, what labor amount should be carried?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass