EstatePass
Contract AdminPermitsmedium20% of exam part

The building department returns plan review comments before permit issuance. What should the GC coordinate?

Correct Answer

C) Responses and revised documents through the design and permit team before work begins

Permit comments must be resolved through the permit/design process before relying on the work for construction.

Answer Options
A
A final payment affidavit because comments are resolved only at closeout
B
A bid withdrawal because comments automatically cancel the construction contract and every subcontract proposal
C
Responses and revised documents through the design and permit team before work begins
D
A supplier invoice because product shipment is the code-response record

Why This Is the Correct Answer

Permit comments must be resolved through the permit/design process before relying on the work for construction.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.