The contract is silent and the permit fee is customarily required for the contractor's execution of the work. What should the GC expect administratively?

Correct Answer

B) The contractor normally secures and pays customary permits and fees unless the contract states otherwise

Contract administration commonly assigns customary post-contract permits and fees to the contractor unless otherwise provided.

Answer Options
A
The inspector pays the fee because the inspector performs inspections
B
The contractor normally secures and pays customary permits and fees unless the contract states otherwise
C
The lender pays the fee outside the project contract without documentation
D
The lowest bidder from bid day pays the fee even if not awarded the work or listed on the permit

Why This Is the Correct Answer

Contract administration commonly assigns customary post-contract permits and fees to the contractor unless otherwise provided.

Why the Other Options Are Wrong

Option A: The inspector pays the fee because the inspector performs inspections

The inspector pays the fee because the inspector performs inspections skips the written authority, scope, price, notice, or release control needed for permit fee responsibility.

Option C: The lender pays the fee outside the project contract without documentation

The lender pays the fee outside the project contract without documentation skips the written authority, scope, price, notice, or release control needed for permit fee responsibility.

Option D: The lowest bidder from bid day pays the fee even if not awarded the work or listed on the permit

The lowest bidder from bid day pays the fee even if not awarded the work or listed on the permit skips the written authority, scope, price, notice, or release control needed for permit fee responsibility.

Memory Technique

Permit Fee square for Reviews Permit-Fee: scope, authority, price, paper.

Reference Hint

Open-book path: tab AIA A201-2017 to Article 3, Β§3.7 Permits, Fees, Notices, and Compliance with Laws; match the role, timing, and required approval before choosing.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.