A notice of commencement was recorded, but no work actually starts for more than 90 days. What should the PM verify before relying on it?
Correct Answer
C) Verify whether the old notice is void before inspections continue
Chapter 713 states that a notice may become void if the improvement does not actually commence within 90 days.
Why This Is the Correct Answer
Chapter 713 states that a notice may become void if the improvement does not actually commence within 90 days.
Why the Other Options Are Wrong
Option A: Whether the original bid bond premium can be reused as the lien-law filing
Whether the original bid bond premium can be reused as the lien-law filing does not satisfy the required party, deadline, proof, license, bond, insurance, or agency trigger for notice effective period.
Option B: Whether the subcontractor schedule of values can extend the recorded notice automatically
Whether the subcontractor schedule of values can extend the recorded notice automatically does not satisfy the required party, deadline, proof, license, bond, insurance, or agency trigger for notice effective period.
Option D: Whether the punch list can replace recording requirements after occupancy
Whether the punch list can replace recording requirements after occupancy does not satisfy the required party, deadline, proof, license, bond, insurance, or agency trigger for notice effective period.
Memory Technique
Good work cannot rewind a missed states trigger in Delayed Permit.
Reference Hint
Open-book path: tab Florida Statutes Chapter 713 to Section 713.13 notice of commencement duration and commencement; confirm the required quantity, authority, timing, or record before selecting the answer.
More Contract Admin Questions
An owner assumes the architect's site visit means the architect is supervising the contractor's crews. What AIA A201 concept corrects that assumption?
The GC and owner disagree about what a specification requires. Under AIA A201, who commonly provides interpretations and decisions during administration?
The architect observes work that does not conform to the Contract Documents. Which AIA A201 architect authority may apply?
A subcontractor says the prime contract general conditions do not apply to its work. Under AIA A401, what should the GC point to?
An addendum adds 18 access panels at $315 each installed. What amount should be added to the bid?
A slab-on-grade is 96 ft by 54 ft and 5 in thick. Including 7% waste, how many cubic yards of concrete should be carried?
An addendum adds 14 doors at $685 each installed. What additive amount should be added to the bid for those doors?
A CMU wall area is 2,240 sf after openings. If one block covers 1.125 sf and 4% waste is included, how many blocks should be estimated?
An office ceiling takeoff is 11,250 sf. Ceiling tile waste is 6%. How many square feet of tile should be carried?
A framing crew averages 310 lf of partition layout and track per day. The bid includes 2,170 lf. At $1,540 per crew day, what labor amount should be carried?