A subcontractor repeatedly misses agreed recovery dates after written coordination efforts. What should the PM do next?
Correct Answer
D) Use the subcontract notice path and preserve schedule-impact records
Subcontract administration uses documented recovery efforts and the contractual notice path.
Why This Is the Correct Answer
Subcontract administration uses documented recovery efforts and the contractual notice path.
Why the Other Options Are Wrong
Option A: Replace the subcontractor immediately without notice, records, or coordination
Replace the subcontractor immediately without notice, records, or coordination does not satisfy the required party, deadline, proof, license, bond, insurance, or agency trigger for subcontract performance notice.
Option B: Ignore the missed dates until final completion has already failed
Ignore the missed dates until final completion has already failed does not satisfy the required party, deadline, proof, license, bond, insurance, or agency trigger for subcontract performance notice.
Option C: Ask an unrelated supplier to certify the subcontractor's schedule recovery
Ask an unrelated supplier to certify the subcontractor's schedule recovery does not satisfy the required party, deadline, proof, license, bond, insurance, or agency trigger for subcontract performance notice.
Memory Technique
Manages Trade envelope: right person, right date, right contents.
Reference Hint
Open-book path: tab AIA A201-2017 to Article 5 subcontractors and Article 15 claims and disputes; confirm the required quantity, authority, timing, or record before selecting the answer.
More Contract Admin Questions
An owner assumes the architect's site visit means the architect is supervising the contractor's crews. What AIA A201 concept corrects that assumption?
The GC and owner disagree about what a specification requires. Under AIA A201, who commonly provides interpretations and decisions during administration?
The architect observes work that does not conform to the Contract Documents. Which AIA A201 architect authority may apply?
A subcontractor says the prime contract general conditions do not apply to its work. Under AIA A401, what should the GC point to?
An addendum adds 18 access panels at $315 each installed. What amount should be added to the bid?
A slab-on-grade is 96 ft by 54 ft and 5 in thick. Including 7% waste, how many cubic yards of concrete should be carried?
An addendum adds 14 doors at $685 each installed. What additive amount should be added to the bid for those doors?
A CMU wall area is 2,240 sf after openings. If one block covers 1.125 sf and 4% waste is included, how many blocks should be estimated?
An office ceiling takeoff is 11,250 sf. Ceiling tile waste is 6%. How many square feet of tile should be carried?
A framing crew averages 310 lf of partition layout and track per day. The bid includes 2,170 lf. At $1,540 per crew day, what labor amount should be carried?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass