A subcontractor repeatedly misses agreed recovery dates after written coordination efforts. What should the PM do next?

Correct Answer

D) Use the subcontract notice path and preserve schedule-impact records

Subcontract administration uses documented recovery efforts and the contractual notice path.

Answer Options
A
Replace the subcontractor immediately without notice, records, or coordination
B
Ignore the missed dates until final completion has already failed
C
Ask an unrelated supplier to certify the subcontractor's schedule recovery
D
Use the subcontract notice path and preserve schedule-impact records

Why This Is the Correct Answer

Subcontract administration uses documented recovery efforts and the contractual notice path.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.