A design element does not comply with the Florida Building Code but appears cheaper. What should the GC do before pricing it as a permit-ready solution?
Correct Answer
B) Treat code compliance as required and seek a compliant design or approved code path
Permit-ready work must be capable of code approval, not merely cheaper.
Why This Is the Correct Answer
Permit-ready work must be capable of code approval, not merely cheaper.
Why the Other Options Are Wrong
Option A: Carry the cheaper noncompliant detail and leave the code conflict for correction during the last inspection
Carry the cheaper noncompliant detail and leave the code conflict for correction during the last inspection does not satisfy the required party, deadline, proof, license, bond, insurance, or agency trigger for code compliance before approval.
Option C: Ask the subcontractor to certify the building department will ignore it
Ask the subcontractor to certify the building department will ignore it does not satisfy the required party, deadline, proof, license, bond, insurance, or agency trigger for code compliance before approval.
Option D: Use the owner's preference as a substitute for code approval
Use the owner's preference as a substitute for code approval does not satisfy the required party, deadline, proof, license, bond, insurance, or agency trigger for code compliance before approval.
Memory Technique
Good work cannot rewind a missed permit-ready trigger in Estimator Notices.
Reference Hint
Open-book path: tab Florida Building Code, Building, 8th Edition (2023) to General code compliance and Chapter 1 administration; match the project role and timing before choosing.
More Contract Admin Questions
An owner assumes the architect's site visit means the architect is supervising the contractor's crews. What AIA A201 concept corrects that assumption?
The GC and owner disagree about what a specification requires. Under AIA A201, who commonly provides interpretations and decisions during administration?
The architect observes work that does not conform to the Contract Documents. Which AIA A201 architect authority may apply?
A subcontractor says the prime contract general conditions do not apply to its work. Under AIA A401, what should the GC point to?
An addendum adds 18 access panels at $315 each installed. What amount should be added to the bid?
A slab-on-grade is 96 ft by 54 ft and 5 in thick. Including 7% waste, how many cubic yards of concrete should be carried?
An addendum adds 14 doors at $685 each installed. What additive amount should be added to the bid for those doors?
A CMU wall area is 2,240 sf after openings. If one block covers 1.125 sf and 4% waste is included, how many blocks should be estimated?
An office ceiling takeoff is 11,250 sf. Ceiling tile waste is 6%. How many square feet of tile should be carried?
A framing crew averages 310 lf of partition layout and track per day. The bid includes 2,170 lf. At $1,540 per crew day, what labor amount should be carried?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
