After review, the architect states the amount properly due to the contractor. What AIA A201 document is involved?

Correct Answer

C) Certificate for Payment

A201 provides for certificates for payment after architect review.

Answer Options
A
Bid addendum
B
Subcontract notice to proceed
C
Certificate for Payment
D
Temporary certificate of occupancy

Why This Is the Correct Answer

A201 provides for certificates for payment after architect review.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.