A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
Correct Answer
D) 140 cy
Volume is 180 x 3 x 7 = 3,780 cf. Dividing by 27 gives 140 cy. Other choices use the wrong depth, add an unsupported allowance, or forget to convert cubic feet to cubic yards.
Why This Is the Correct Answer
Volume is 180 x 3 x 7 = 3,780 cf. Dividing by 27 gives 140 cy. Other choices use the wrong depth, add an unsupported allowance, or forget to convert cubic feet to cubic yards.
Why the Other Options Are Wrong
Option A: 126 cy
trench excavation volume, choice a: 126 cy equals about 3,402 cf after cubic-yard conversion; the accepted cubic-foot volume is 3,780 cf before dividing by 27 in.
Option B: 147 cy
trench excavation volume, choice b: 147 cy equals about 3,969 cf after cubic-yard conversion; the accepted cubic-foot volume is 3,780 cf before dividing by 27 in.
Option C: 420 cy
trench excavation volume, choice d: 420 cy equals about 11,340 cf after cubic-yard conversion; the accepted cubic-foot volume is 3,780 cf before dividing by 27 in.
Memory Technique
Picture a gate labeled trench excavation volume: finish every operation before accepting 140 cy.
Reference Hint
Open Pipe and Excavation Contracting, 2011; use the index entry or section for "Trench excavation quantity takeoff" to confirm that Volume is 180 x 3 x 7 = 3,780 cf.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
Nineteen steel deck sheets each cover 31 sq ft. What total coverage is available before waste?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A punched window is set before the sill flashing membrane is lapped into the rough opening. The WRB is already cut around the opening. What should the crew do?
Next Question
A bid is $1,280,000, and the bid instructions require bid security equal to 5 percent of the bid. What bid bond amount is required?