A roofing foreman checks the substrate condition: what supports payment for stored materials?
Correct Answer
A) Contract-required evidence such as invoice, storage, insurance, and project allocation
Contract-required evidence such as invoice, storage, insurance, and project allocation is the controlling requirement: the distractors are related-looking contract or field terms, but they do not match the cited requirement for review item 143.
Why This Is the Correct Answer
Contract-required evidence such as invoice, storage, insurance, and project allocation is the controlling requirement
Why the Other Options Are Wrong
Option B: Base the stored materials response on a verbal promise
Choice B (A verbal promise only) is rejected because the action skips the timing, documentation, or field-control step needed for Stored materials.
Option C: Classify the condition as a bid-tab note, leaving stored materials unverified
In procurement and contracting, A bid-tab note is the wrong selection for Stored materials: it names a financial document or payment mechanism, not the Stored materials action/result stated by.
Option D: Classify the condition as a deleted submittal
The trap in D is A deleted submittal. That selection is wrong because the option tries to substitute, waive, or delete the Stored materials control; the item instead requires.
Memory Technique
Make stored materials a tabbed card: cite the exact condition, then choose Contract-required evidence such as invoice, storage, insurance, and project allocation.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Stored-material payment" to confirm that Contract-required evidence such as invoice, storage, insurance, and project allocation is the controlling requirement
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
