Why are backfill lifts limited in thickness?
Correct Answer
A) Compaction equipment must be able to densify the full lift depth.
Excessive lift thickness can leave loose soil below the compacted surface.
Why This Is the Correct Answer
Excessive lift thickness can leave loose soil below the compacted surface.
Why the Other Options Are Wrong
Option B: Thicker lifts always compact better
In site construction, Thicker lifts always compact better. is the wrong selection for Lift thickness control: it points to Thicker lifts always compact better. but.
Option C: Treat lift thickness limits as only decorative
The trap in C is Lift thickness is only decorative. That selection is wrong because the option delays or omits the controlling step.
Option D: Treat lift thickness limits as only affecting paint warranty
Choice D gives It only affects paint warranty. Its specific error: the action skips the timing, documentation, or field-control step needed for Lift thickness control.
Memory Technique
Picture lift thickness control doing the job; the answer names that job as Compaction equipment must be able to densify the full lift depth.
Reference Hint
Open Pipe and Excavation Contracting, 2011; use by topic index - bedding / backfill / compaction to confirm that Excessive lift thickness can leave loose soil below the compacted surface.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?