The owner wants to direct-purchase major equipment to save tax, but the contractor is still responsible for coordination and installation. What must be clarified before release?
Correct Answer
C) Responsibility for ordering, delivery risk, warranties, storage, installation, and schedule impacts
Owner direct-purchase arrangements should clarify procurement, risk, warranty, storage, installation, and schedule responsibilities. Other choices ignore the issues that cause scope and payment disputes.
Why This Is the Correct Answer
Owner direct-purchase arrangements should clarify procurement, risk, warranty, storage, installation, and schedule responsibilities. Other choices ignore the issues that cause scope and payment disputes.
Why the Other Options Are Wrong
Option A: Clarify only the owner's preferred supplier name on the release form
The trap in A is Only the owner's preferred color. That selection is wrong because it leaves the work at an informal or incomplete stage, while Owner direct purchase requires Responsibility for ordering, delivery risk, warranties, storage, installation, and schedule impacts; Owner-purchased items require clear responsibility for procurement, delivery.
Option B: Clarify only the supplier's ship date, not risk or warranty terms
Choice B gives Only the supplier's holiday schedule. Its specific error: the option delays or omits the controlling step.
Option D: Clarify only the purchase-order number, not delivery or storage responsibility
In procurement and contracting, The final punch-list font size is the wrong selection for Owner direct purchase: the choice would not get the project to Responsibility for ordering, delivery risk, warranties, storage, installation, and schedule impacts, which is the Owner direct purchase result verified by the source.
Memory Technique
Remember owner direct purchase by its jobsite consequence: the correct move points to Responsibility for ordering, delivery risk, warranties, storage, installation, and schedule impacts.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management - Basic, 14th Ed.; use by topic index - procurement and contracting fallback to confirm that Owner direct-purchase arrangements should clarify procurement, risk, warranty, storage, installation, and schedule responsibilities.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A temporary water tank contains 1,250 gallons during a pressure test. Using 8.34 lb/gal, what water weight should be considered?
Next Question
A deck installer checks the fastening plan: a project records 4 recordable cases over 85,000 work hours. Using the 200,000-hour multiplier, what incident rate is closest?
