A deck installer checks the fastening plan: a project records 4 recordable cases over 85,000 work hours. Using the 200,000-hour multiplier, what incident rate is closest?
Correct Answer
D) 9.4
The calculation gives 9.4 for the stated incident rate. Other choices: the distractors come from omitting an adjustment, using the wrong rate, or applying a rounded shortcut for calculation item 177.
Why This Is the Correct Answer
The calculation gives 9.4 for the stated incident rate.
Why the Other Options Are Wrong
Option A: 9.4 (unadjusted)
incident rate, choice a: 9.4 (unadjusted) repeats the numeric result but changes the required label or rounding; 4 x 200000 / 200,000 = 4. so the keyed form is 9.4.
Option B: 8
incident rate, choice c: 8 backs into 8 when divided by 200000 / 200000; the accepted setup gives 9.4 on that same base.
Option C: 10
incident rate, choice d: 10 backs into 10 when divided by 200000 / 200000; the accepted setup gives 9.4 on that same base.
Memory Technique
Picture a ledger line labeled incident rate: finish every operation before accepting 9.4.
Reference Hint
Open 29 CFR 1926 OSHA Construction Standards; use the index entry or section for "incident rate calculation" to confirm that The calculation gives 9.4 for the stated incident rate.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
The owner wants to direct-purchase major equipment to save tax, but the contractor is still responsible for coordination and installation. What must be clarified before release?
Next Question
Inside a controlled decking zone, the foreman tracks panels that have been laid but not finally secured. What OSHA cap applies to unsecured decking in the CDZ?