The erector asks what temporary stability load the column anchor-rod assembly must resist. Which OSHA value and eccentricity are specified?
Correct Answer
C) 300 lb at 18 in.
OSHA 1926.755(a)(2) requires the column anchor-rod assembly to resist a minimum eccentric gravity load of 300 lb located 18 in. from the extreme outer face of the column in each direction at the top of the column shaft. Other choices change either the load or the eccentricity.
Why This Is the Correct Answer
OSHA 1926.755(a)(2) requires the column anchor-rod assembly to resist a minimum eccentric gravity load of 300 lb located 18 in. from the extreme outer face of the column in each direction at the top of the column shaft. Other choices change either the load or the eccentricity.
Why the Other Options Are Wrong
Option A: 150 lb at 12 in.
The trap in A is 150 lb at 12 in. That selection is wrong because 150 lb at 12 in. is a different published number than the cited Anchor rod design load value; 29 CFR 1926.755(a)(2) supports 300 lb at 18 in.; Column anchor-rod assemblies must resist a 300 lb eccentric gravity load at 18 in.
Option B: 200 lb at 24 in.
Choice B gives 200 lb at 24 in. Its specific error: 200 lb at 24 in. is a different published number than the cited Anchor rod design load value; 29 CFR 1926.755(a)(2) supports 300 lb at 18 in. The accepted answer is 300 lb at 18 in.
Option D: 500 lb at 18 in.
In metals work, 500 lb at 18 in. is the wrong selection for Anchor rod design load: 500 lb at 18 in. is a different published number than the cited Anchor rod design load value; 29 CFR 1926.755(a)(2) supports 300 lb at 18 in.
Memory Technique
File anchor rod design load under a fastener row: condition first, number or duty second, answer 300 lb at 18 in.
Reference Hint
Open 29 CFR Part 1926, Subpart R - Steel Erection; use 29 CFR 1926.755(a)(2) to confirm that OSHA 1926.755(a)(2) requires the column anchor-rod assembly to resist a minimum eccentric gravity load of 300 lb located 18 in.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
The fire-resistance-rated wall detail calls for Type X gypsum board. Which board thickness is commonly associated with Type X wallboard in rated assemblies?
Next Question
The field office receives a written instruction: at what excavation depth is a protective system generally required unless an exception applies?
