The erector asks what temporary stability load the column anchor-rod assembly must resist. Which OSHA value and eccentricity are specified?
Correct Answer
C) 300 lb at 18 in.
OSHA 1926.755(a)(2) requires the column anchor-rod assembly to resist a minimum eccentric gravity load of 300 lb located 18 in. from the extreme outer face of the column in each direction at the top of the column shaft. Other choices change either the load or the eccentricity.
Why This Is the Correct Answer
OSHA 1926.755(a)(2) requires the column anchor-rod assembly to resist a minimum eccentric gravity load of 300 lb located 18 in. from the extreme outer face of the column in each direction at the top of the column shaft. Other choices change either the load or the eccentricity.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
A rooftop unit schedule lists capacity in tons of cooling. In HVAC estimating, one ton of cooling equals what heat-transfer rate?
The bid form asks for a base bid and three alternates. How should the contractor submit alternate pricing?
A specification includes a $40,000 hardware allowance because final selections are pending. How is the allowance treated in the bid?
The earthwork section requires unit prices for unsuitable-soil removal. What is the contract-administration use of those unit prices?
Before the first progress payment, the owner requests a schedule of values. What is its main contract-payment function?
A signed change order is issued for added lobby millwork. Which contract effect should it state?
On the finish plan, locate room R358; then use the finish schedule. What remarks is listed?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
The fire-resistance-rated wall detail calls for Type X gypsum board. Which board thickness is commonly associated with Type X wallboard in rated assemblies?
Next Question
The field office receives a written instruction: at what excavation depth is a protective system generally required unless an exception applies?
